Aquatic centre development taking shape
There’s been noticeable progress made at the new aquatic centre development on Portia Street.
Over the last few months a number of construction milestones have been reached, these include:
- excavation (digging holes!) for the new pools and foundations
- pouring of foundations and pool floors
- drainage and plumbing for the dry areas of the aquatic centre, such as the offices and club room.
The project is tracking well and we’re on target to be diving into the deep end (or popping a manu if that’s more your style) before the end of 2022.
You can see photo and video updates, as well as a floor plan of the development on our projects page.
Council would like to thank the Provincial Development Fund, Taranaki Electricity Trust and Toi Foundation for their financial support towards this community asset.